Start here: the brief
This is Part C of the assessment and carries 100 marks. You build the 2027 internal audit programme, plan two audits, run them on an evidence pack of 14 exhibits, hold the meetings, report, and decide on two corrective action responses, the way you would on a real site. Parts A and B are the two online quizzes in the same module. You need 70 percent in each part to pass.
The case study
The case is a training scenario built from real audit patterns. No real company is named.
The people on site
| Name | Role | Department | Audit training |
|---|
How Part C is marked
| Step | What is checked | Marks |
|---|---|---|
| 1. Observations | The auditing principles at risk in the steering meeting, and what the site should do about them, in your own words. | 8 |
| 2. Audit programme | Frequency from the site’s own scoring rule; the right number of audits scheduled; trained auditors who do not audit their own work or department; approval details. | 8 |
| 3. Audit plans | Objectives, criteria and scope for each audit; opening meeting first and closing meeting last; times in order; every source of evidence planned; the night shift seen on night shift. | 8 |
| 4. Opening meetings | Every item completed for both audits; the classification of findings explained; closing meeting times that match your plans. | 4 |
| 5. Evidence pack | A decision on all 14 exhibits; the planted nonconformities found against the right clause; no finding where the site conforms; the out of scope matter referred; evidence and a statement in your own words. | 40 |
| 6. Closing meetings | Every item completed; the number of findings matching your evidence pack; the corrective action route and who verifies closure. | 4 |
| 7. Report and corrective action | Report sections, conclusion and distribution; an owner and a due date on every nonconformity; the two corrective action responses decided and reasoned against 10.2. | 18 |
| Consistency | Your programme, plans, meetings and report describe the same two audits, against the same criteria, on the same dates. | 10 |
Step 1: Observations on the steering meeting
Read the fourth paragraph of the case again. Which principles of auditing (ISO 19011:2026, 4.2 to 4.8) are put at risk by what Nomvula and Anneke proposed? Select only the ones that apply.
Step 2: Internal audit programme for 2027
| Process and facts | Owner | Imp. | Prev. | Chg. | Audits a year | Auditor | J | F | M | A | M | J | J | A | S | O | N | D |
|---|
Step 3: Audit plans
Step 4: Opening meetings
Write what you would say or confirm for each item, in short sentences.
Step 5: The evidence pack
Step 6: Closing meetings
Step 7: Audit report and corrective action
5. Nonconformities and corrective action requests (built from step 5)
| Ref | Exhibit | Clause | Statement | Owner | Due date |
|---|
Two corrective action responses
Step 8: Review and submit
There is nothing to download and nothing to upload. Your mark and feedback appear here within a minute and go onto your course record by themselves. We email you the same feedback with your completed audit document attached, so you can keep it or print it.